Construction daily log: what to record every day
Short answer: A construction daily log (also called a daily report or superintendent's daily) records, for each working day, the weather, the crews and headcount on site by company, equipment used or idle, work performed by area, materials delivered, inspections and visitors, delays and their causes, safety events, and any instructions received. Write it the same day, keep it factual, attach photos, and file it where it can't be quietly edited later.
Nobody enjoys writing the daily at 5:30 in the afternoon. But when a delay claim lands eighteen months later, the dailies are often the only record of what actually happened on a given Tuesday. Attorneys and claims consultants read them line by line. A superintendent who wrote "rain, no work" every wet day, with headcounts, is in a much better spot than one who skipped the bad days.
Who keeps the daily log
On most jobs the GC's superintendent owns it. Subcontractors often keep their own foreman's dailies and may be required to submit them to the GC. Owner's reps and construction managers sometimes keep a parallel log. Check the contract: many general conditions and specs require the contractor to keep daily reports and make them available to the owner, and some spell out the format.
What to record each day
Weather and site conditions
Record conditions at start of day and any change during the day: temperature, precipitation, wind, and ground conditions. "Rain from 10:15 to 13:00, 0.4 in. per site gauge. Site muddy, excavation at Area B flooded, pumping until 14:30." Weather days are among the most argued items in delay claims, so record the effect on the work as well as the weather itself.
Manpower
Headcount by company and trade, and hours if you can get them. "ABC Electric: 1 foreman, 4 journeymen, 2 apprentices, 8 hrs." Note when a sub is short-crewed against what they committed to in the schedule. That's the start of a paper trail if their progress slips.
Equipment
Major equipment on site, whether it worked or sat idle, and why. Idle equipment caused by a delay can be part of a cost claim, but only if someone wrote down that it was there and idle.
Work performed
By area and activity, tied to schedule activities where possible. "Level 3 east: deck pour complete, 112 CY, placed 07:00 to 11:40." "Units 301 to 306: drywall hang 80% complete." Specific quantities and locations beat "continued framing."
Materials and deliveries
What arrived, from whom, and anything rejected or damaged. Late deliveries that held up a crew deserve their own line.
Inspections, tests and visitors
Building department inspections and results, special inspections, concrete cylinders taken, owner and design team visits. Name the inspector or visitor and their company. If an inspection failed, note the reason and the reinspection date.
Delays, problems and instructions
Anything that stopped or slowed the work: waiting on an RFI response, a design conflict, a utility strike, an access issue, owner-directed changes. Note the time, who was affected and for how long. If someone gave a verbal instruction that changes the work, write down who said what and when, then follow up in writing. Verbal changes that never got documented are a common source of disputes.
Safety
Toolbox talk topic and attendance, incidents and near misses, first aid, and any OSHA or insurance visits. Keep it factual and leave detailed incident investigation to your safety program's forms. For walk-through findings, see the jobsite safety inspection checklist.
Photos
A handful of dated photos each day, showing overall progress and anything unusual. Photos of conditions before they're covered up (underground, in-wall, under-slab) are the ones people wish they had later.
Daily log template
Daily report fields
- Project, job number, date, day of week, report number
- Prepared by
- Weather: AM / PM, temperature, precipitation, wind; effect on work
- Manpower: company, trade, headcount, hours
- Equipment: on site, working or idle, reason
- Work performed: area, activity, quantity
- Deliveries: supplier, material, issues
- Inspections and tests: type, inspector, result
- Visitors: name, company, purpose
- Delays and problems: cause, time lost, crews affected, RFI or notice reference
- Instructions and changes received: from whom, what, follow-up
- Safety: toolbox talk, incidents, near misses
- Photos with captions
- Signature
Why the daily log matters in claims and disputes
Contemporaneous records, meaning records made at the time, carry much more weight than recollections assembled after a dispute starts. Daily logs typically come up in:
- Delay and time extension requests, to show what was actually affected and for how long.
- Change order pricing, to back up labor and equipment claimed on extra work.
- Back-charges between GC and subs, to show who was on site and what they did.
- Defect claims years later, to show when work was installed and who inspected it.
- Injury claims, to show who was on site and what safety meetings happened.
A few habits make a log more credible. Write it the same day. Don't go back and change entries; add a dated correction instead. Be consistent, including on boring days. And stick to facts. "Sub's crew was lazy" helps nobody; "Drywall crew of 3 on site, schedule shows 8" is evidence. This isn't legal advice, and your contract's notice provisions still apply: a daily log entry usually doesn't count as formal notice of a delay or claim.
Common mistakes
- Copying yesterday's report and forgetting to change half of it.
- Skipping rain days or weekends when work was done.
- Recording "delays" with no cause, duration or affected crew.
- Logging a verbal change and never sending the written follow-up.
- Keeping the log on paper in the trailer, where it can get wet, lost or rewritten.
A phone app that timestamps entries and photos, and works without signal, removes most of these problems. Keep the log somewhere it can't be quietly rewritten, and back it up.
If you're the visitor rather than the super, you want a field report instead. Weekly OAC meeting minutes often pull from the week's dailies.
Visiting the site rather than running it?
Arazim Reports is built for the visitor's side: field observation reports, punch lists and meeting minutes, with photos and your signature, in a PDF on your letterhead. Works offline.
Start free trial 14 days free, no credit card. Then $10/month for your first year.FAQ
Is a daily log the same as a daily report?
On most jobs the terms are used interchangeably. Some firms use "log" for the running internal record and "report" for the version sent to the owner. The content is the same: weather, manpower, equipment, work performed, deliveries, inspections, delays and safety.
Who is responsible for the construction daily log?
Usually the general contractor's superintendent. Subcontractor foremen often keep their own dailies, and construction managers or owner's reps may keep a separate log. Your contract and specifications may require a specific format.
Do I need a daily log on days with no work?
Yes, if the site was scheduled to work. A short entry such as "No work, rain, site closed by super at 07:30" is exactly the kind of record that matters in a weather delay claim.
Can I edit a daily log after it's submitted?
Avoid changing the original. If something was wrong or missing, add a dated correction or addendum that references the original entry. Edits that change history can hurt credibility in a dispute.
Does a daily log entry count as notice of delay?
Usually not by itself. Most contracts require written notice in a specific form and within a set time. Use the daily to document the facts, and send formal notice as your contract requires.